Fully Automated Pharmaceutical Warehouse

two-images-1.jpg

Fully Automated Pharmaceutical Warehouse
Project: Fully Automated Pharmaceutical Distribution Center
Client: Al Dawaa Pharmacies
Location: Riyadh, Saudi Arabia
Year:
• Phase 1: 2021
• Phase 2: 2023

Scope: Design, Supply, Installation and Commissioning of Fully Automated Pharmaceutical Distribution Center.

    Phase 1:
    • A‐Frame SDA System with approximately 1.320 channels
    • OSR Shuttle System Conveyors
    • OSR Shuttle System with 2 aisles, 23 modules, 30 levels (27.600 static locations)
    • Totes for the OSR Shuttle System (36.480 totes)
    • Conveyors including tote buffer, manual stations, loop, spiral conveyor and empty tote handling
    • Stacker/Destacker
    • Vertical Conveyors
    • Lid Turning Device
    • Strapping machine
    • Scale
    • LBA Label printing station
    • Hardware, Software including KiSoft SCADA, SPS , Network, RF Hardware and Software‐licenses
    • Testing and OnSite Assistance
    • CIT Customer Integration Tests
    • Extension of OSR Shuttle system on 2nd level
    • SDA with 1,320 channels on 2nd level
    • RFX Scanners Hardware including set‐up for 2nd level
    • Flow rack channels on the OSR for the support of the SDA on 2nd level
    • Tote conveyor connection on 2nd level
    • PLC Hardware including Installation for 2nd level"
    • Single Wire Network
    • Serialization of SDA and OSR System
    • Invoice Station ABB for document insertion

    Phase 2: Shuttle system Extension
    • Mechanical/electrical components for Pack-to-Patient lines (P2P)
    • Vision control stations
    • Manual induction workstations
    • Label printing and application devices
    • Sorting unit and bagging unit (biodegradable plastic)
    • General hardware & software
    • PLC
    • Full Integration to SAP EWM


two-images-1.jpg